Weekly Briefs

From: Allen Howe
October 23, 2007

More Streets Cleared for Hookup

On Monday, October 29, City Engineer Bill Bayne and the Desert Water Agency (DWA) approved Chuperosa Lane, Sharpless Road, Nightingale Road and Las Tunas Way for sewer connection in the Cove.

Once proof that DWA fees have been paid is received, the City can issue a hookup permit on these and previously approved streets. The Building Department has a list of all of the Cove property owners showing whether or not they have already paid the DWA fee.

The City Engineer and DWA will continue to approve sewer connections for the Cove project every few weeks. I will email you as soon as additional streets are approved for connection and the letters have been mailed to the property owners.

In Dream Homes every home in the neighborhood can now connect!

Fountain of Life Closed for Repair

The Fountain of Life in Town Square has been closed to repair the soft surface around it. The fountain was designed to be interactive. Children (of all ages) play and cool off in the fountain throughout the hot summer months. The soft surface asks as a sort of cushion softening the ground. The fountain will be closed for most of November.

Businesses Off and Running

The Burlington Coat Factory, 99 cent Store, and Sonic Burger have all recently opened their doors for business bringing more shopping and eating experiences to Cathedral City and generating much needed sales tax. Stay tuned for more new businesses opening here in Cathedral City.

Public Workshop to Revise Housing Element of General Plan Next Monday

The City will hold a community workshop as it begins to update the Housing Element of its General Plan. The workshop, which is open to the public, will be held Monday, November 5, 2007 at 6 PM at the Cathedral City Hall Study Session Room (68-700 Avenida Lalo Guerrero).

The Housing Element of the General Plan is the City’s roadmap for meeting its housing needs. The updated Housing Element must demonstrate that the City is prepared to accommodate the development of its “fair share” of the region’s future housing needs (over the 7-year period between 2006 and 2014). In the case of Cathedral City, the housing element will need to show that the City is prepared to accommodate the development of 3,329 new homes and that at least 1,324 of these be affordable to lower income households.

The City has contracted with Terra Nova Planning and Research to prepare the update of the Housing Element, which, by state law, must be written and approved by July 1st 2008. Cathedral City seeks public input on ways to meet its fair share of the future housing needs in the Coachella Valley.

Call 760-770-0376 for more information.

Shredding/Hazardous Waste/Tire Recycling Event this Weekend

The next Stop Identify Theft Shredding Event will be Saturday, November 3 from 9 AM until Noon in the parking lot next to the Desert IMAX Theatre at 68-510 East Palm Canyon Drive.

A Household Hazardous Waste Collection Program event will be held Friday and Saturday, November 2nd & 3rd, from 9 AM until 2 PM for cathedral City residents. The drop off is located at Buddy Rogers Avenue next to the 2nd Street Park.

A Tire Recycling Collection Event where you can dispose of residential tires (passenger and light truck) at no charge will also be held Friday and Saturday, November 2nd & 3rd from 9 AM until 2 PM. The drop off is located at Buddy Rogers Avenue next to the 2nd Street Park. There is a maximum of nine tires per trip.

Important Cathedral City Cove
Phase 1
Construction Information
for the week of October 29, 2007


Project Status Map

Accomplishments

bullet

668 of approximately 750 laterals completed to-date
(89% Complete)

bullet

7.5 of approximately 8 miles of sewer mainline constructed to-date
(94% Compete)

bullet

The project is on schedule.

SEWER CONNECTIONS APPROVED:

Property Owners have been sent a letter from the City Engineer letting them know that they can connect to their new sewers in the following areas:

bullet

“D” Street

bullet

“E” Street

bullet

 “F” Street

bullet

San Jacinto Road
(between East Cathedral Wash and Cathedral Canyon Drive)

bullet

“H” Street

bullet

Iroquois Street

bullet

“J” Street

bullet

Glenn Avenue

bullet

Encelia Lane

bullet

Van Fleet Avenue

bullet

Chuperosa Lane

bullet

Sharpless Road

bullet

Nightingale Road

bullet

Las Tunas Way

The City Engineer will continue to approve connections in the Cove Phase 1 project every few weeks. Letters are mailed to property owners as Desert Water Agency and the City Engineer accept and approve the sewers for connection.

Property owners, who also occupy their home in the Cove neighborhood, may qualify for financial assistance for the connection process from Cathedral City Redevelopment Agency Affordable Housing funds. Please call 760-770-0376 for more information.

WORK SCHEDULED WEEK OF OCTOBER 29, 2007:

The list below represents the best available information for work scheduled during the upcoming week of October 29, 2007. The contractor regularly provides door hanger notices on streets prior to work being where construction is planned.

SEWER WORK IN PROCESS

Sewer mainline, lateral and manhole installation will be done on the following streets:

bullet

East Palm Canyon Drive (between Sunair Plaza and Bankside Drive)

bullet

Palo Verde Drive
(between East Palm Canyon Drive and Tahquitz Road)

bullet

Sunair Plaza (between Commercial Road and Bankside Drive)

bullet

Melrose Drive
(between Commercial Road and East Palm Canyon Drive)

There will “No Street-side Parking” allowed on Sunair Plaza from Commercial Road to Bankside Drive this week starting on Monday, October 29nd from 6 am to 6 pm.

“No Parking” signs will be posted. Please have cars at your location park on your property during these times. Businesses and property owners are encouraged to use the City Hall parking structure for parking if on-site parking is not adequate.

STORM DRAIN WORK IN PROCESS

Storm drain pipe, catch basin and manhole installation will be done on the following streets:

bullet

Tahquitz Road
(between Cathedral Canyon Drive and Palo Verde Drive)

bullet

Cathedral Canyon Drive
(between Tahquitz Road and H Street)

bullet

Palo Verde Drive
(between E. Palm Canyon Drive and Tahquitz Road)

STREET WORK IN PROCESS

Street and paving preparation will be done on the following street:

bullet

Bankside Drive
(between Sunair Plaza to East Palm Canyon Drive)

bullet

Commercial Road
(between Cathedral Canyon Drive to Bankside Drive)

bullet

Sunair Plaza
(between E. Palm Canyon Drive and Bankside Drive)

bullet

Melrose Drive
(between Commercial Road and East Palm Canyon Drive)

Street Paving Completed To-Date:

bullet

“D” Street

bullet

“E” Street

bullet

“F” Street

bullet

“H” Street

bullet

“J” Street

bullet

San Jacinto Road
(west of Van Fleet Avenue)

bullet

Iroquois Street

bullet

Van Fleet Avenue

bullet

Glenn Avenue

bullet

Terrace Road

bullet

Bel Air Drive

bullet

Paradise Way

bullet

Mountain View Road

bullet

Desert View Road

bullet

Chuperosa Lane

bullet

Las Tunas Way

bullet

Nightingale Road

bullet

Sharpless Road

bullet

Indigo Lane

bullet

Hillcrest Road

bullet

Moonlight Drive

bullet

Treasure Trail

bullet

Dorn Road

bullet

Vista Drive

bullet

Vicky Lane

bullet

Chris Drive

bullet

Kathy Drive

bullet

Rodeo Road

bullet

Porter Drive

bullet

Palo Verde Drive
(between Terrace Road and Hillcrest Road)

bullet

Cathedral Canyon Drive
(between East Palm Canyon Drive to Officer David Vasquez Drive)

Note:

Cove residents may see construction workers in areas throughout the Phase 1 Cove project that have been paved. This work could be related to surveying, material testing, inspection, contractor punch-list items, and field conditions resulting in unplanned work activity.

For more information on the Cove Improvement Project
please call the
COVE HELPLINE: (760)  250-8673
Click here for more information
Cove Improvement District Home Page

 

Dream Homes
Construction Update
Week of October 29, 20076

Sewer service is available to EVERY HOME in the neighborhood!

All homes may now connect!

Detailed information on HOW TO CONNECT has been mailed to property owners and is also available by calling (760) 770-0348!

Project Status/Upcoming Construction:

Sewer Construction: Complete
Water Construction: Complete
Restoration: Complete
Punch List: In progress
Paving: Will resume on 11.19.07—starting on San Luis Rey!
Manhole/valve adjustments: Will begin on 11.26.07
Project Timetable: On schedule!

DREAM HOMES HELPLINE: (760)  770-0348

Click here for more information
Dream Homes Improvement District Home Page

Updated 11/07/2007

##