City of Cathedral City
68700 Avenida Lalo Guerrero
Cathedral City, CA 92234
(760) 770-0340

Weekly Briefs

From: Allen Howe
September 25, 2007

Status Report: Cove Project is On Time and Within Budget

Phase 1 of the Cove sewer and street improvement project is on schedule to be completed by the end of this year and is within the approved budget.

Eighty-five percent of the first phase of the comprehensive effort to replace aging septic systems with public sewers, install new water lines, storm drains and provide street reconstruction, including driveway approaches and curb and gutter, is complete.

638 of approximately 750 laterals and seven of eight miles of sewer mainline pipe have been constructed to date.

Owners have begun connecting their properties to the sewer. Properties from D Street to “J”, between Cathedral Canyon Drive and the east Cathedral Wash have been approved by the city engineer and Desert Water Agency for connection to the new the public sewer. As of last Wednesday, 21 properties had been connected to the new laterals and mains. Another 150 are eligible to hook up and were sent letters in mid-September letting them know they are now approved for connection to the sewer.

Connection letters are mailed to property owners after Desert Water Agency and the city accept and approve the sewer work.

The letters also provide notice that property owners, who also occupy their home in the Cove, may qualify for financial assistance for the connection from the Redevelopment Agency’s affordable housing funds.

Street paving is on schedule. Terrace Road, the Cove’s main east-west route, was paved last week, a major step in making it easier for residents to navigate throughout the neighborhood. The reason Terrace has taken several months to complete is because construction there is more comprehensive than in the other streets. It included sewer installation, storm drain work with a 54” diameter pipe and catch basins, new water lines, a ribbon gutter in the center of the street, new curbs, gutters and driveway approaches.

Currently, the only streets remaining to be paved in the first phase are Cathedral Canyon Drive and streets south of Kings Road to the North Cathedral Wash. These are now having sewer, water line and storm drain work done and will be paved when that work is finished.

Detours for the project are adjusted daily to accommodate changes in locations where crews are working and material and concrete cure time.

This project involves many separate types of work – digging trenches, installing sewer main lines and laterals to serve each property, putting in water lines (with minimum 10’ separation from sewers), constructing storm drains and catch basins, grading, pouring concrete, laying asphalt and installing curbs, gutters and driveway approaches. When residents see a trench being dug in front of their house, they might expect the water line or sewer main to be installed immediately after, perhaps by the same crew, followed by pouring of curbs and gutters and then the street work.

However, in reality, after the initial crew digs the trench, it moves up or down the street performing the same task, while the workers laying pipelines are doing that elsewhere in the project. It is more productive and cost effective for crews performing a certain task, such as installing sewers, to work sequentially for long periods on that task without interruption and without changing tasks.

Construction work hours during the summer started at 6 am and ended between 3 and 4 pm. Construction hours as of October 1st per City Ordinance will start at 7 am. The hours of construction for rest of this phase will be roughly 7 am to 4 pm.

Most of the remaining 15% of construction left to be done is happening now in the commercial district north of East Palm Canyon.

Several weeks prior to construction on a street, notices are mailed to each property owner and resident by the city engineer outlining the construction process, potential impacts to trash service, mail delivery, construction hours and street parking limitation, along with project contact information.

In addition, the contractor provides door hangers identifying construction activity dates with project contact information.

The City’s project team responds to all resident concerns through the Cove Helpline phone number and through email. Field meetings are set up with individual property owners to address individual concerns as needed.

For the second phase of the Cove project, final plans are being completed. The plans will be bid later this year and it is anticipated that construction for the second phase will start early in 2008. The 2nd phase will include sewer installation, water lines, storm drains, curbs, gutters and driveways for the properties in the Cove in the area above Grandview Avenue and on Charlesworth.

Since Terrace Road and Cathedral Canyon are being done as part of the first phase of construction, the detours for the second phase will affect mostly local neighborhood streets, with less impact on the overall neighborhood.

To bid the project, the documents for the second phase will be posted on the City’s website, making it convenient for potential bidders to pull up data and plans for the project. Sets of plans are also placed in plans rooms throughout the Southland. Since the web site was implemented for this purpose several months ago, interest in bidding on city public works projects has increased substantially. The more bids submitted, the more likely it is that they will be competitive and come in within budget.

Following bid solicitation, submittal of bids, evaluation and award by City Council to the lowest responsible bidders, construction on Phase 2 could begin as early as March 2008. Work in the primarily upper Cove second phase should take about 18 months and is scheduled for completion in 2009.

While this work is a major disruption in the lives of Cove property owners, it should be kept in mind that infrastructure is normally installed in a neighborhood before people move in. The extent of the tearing up and rebuilding in an already developed area makes it all the more inconvenient.

However, with public sewers, water line upgrades, new streets and storm drain improvements and judging from the improved appearance of the streets that are finished, it should be worth the aggravation. The project also meets State requirements to eliminate septic tank usage in the Cove by January 1, 2012, in an effort to protect the underground aquifer that serves the entire region.

Architectural Review Committee Update

At its September 12 meeting, City Council appointed Randy Purnel to fill a vacancy on the Architectural Review Committee (ARC). Purnel is a licensed Landscape Architect with10 years experience in electrical and general construction. At its September25th meeting the ARC re-elected Kendra Culbertson as Chair and John Holt as Vice Chair.

Cans for Cash

The third annual Cans for Cash Recycling Challenge, sponsored by the Cathedral City Environmental Conservation Division, the United States Conference of Mayors, Burrtec Waste & Recycling Services and S.C.R.A.P Gallery, is October 1st – 28th. The Challenge is a month long contest that rewards schools for recycling bottles and cans. For more information contact the Cathedral City Environmental Conservation Manager at 760-770-0369.

Fire Department Annual Open House October 13th

The Cathedral City Firefighters Association will be cooking up their famous pancakes at the 19th Annual Open House and Pancake Breakfast on Sat. Oct. 13, 8am-11am, at the Cathedral City Fire Administration Building, 32-100 Desert Vista Rd., 3 blocks west of Date Palm Drive.

The department will have an array of activities, and demonstrations at the Open House including “Stop, Drop, & Roll”, face painting, balloons, blood pressure checks and SPARKY! The Community Blood Bank will be joining the festivities for a four hour blood drive.

##