Weekly Briefs

From: Allen Howe
April 3, 2007

Electronic Waste Collection for Cathedral City Residents

There will be an electronic waste collection event for residents and businesses located in Cathedral City this Saturday, April 7, 2007 from 9 AM until 12 PM in the front parking lot of Lowe’s Home Improvement Center in Palm Springs (5201 E. Ramon Road). Bring your computers, monitors, keyboards, printers, telephones and cell phones, answering machines, fax machines, televisions and microwaves. The electronic material is dismantled and recycled. Any information stored on hard drives or cell phones is destroyed during the processing phase.

You no longer have to wait for our April and November electronic waste collection events. Every Tuesday from 1 PM – 3PM the Cathedral City Public Works Yard (68-385 Kieley Rd.) will accept electronic waste from Cathedral City Residents.

The next Stop Identity Theft shredding event will be Saturday May 5 from 9 AM to 12 PM next to the Desert IMAX Theatre.

Energy Conservation Fair

Come visit the Coachella Valley’s first Energy Conservation Fair on Earth Day Weekend (April 21st and 22nd) at the College of the Desert (43500 Monterey in Palm Desert) adjacent to the Street Fair.

Take advantage of energy saving programs and services such as energy efficient products and incentives, energy star appliance rebates, low-income programs, home energy saving tips, residential energy retrofits, PV solar demonstrations, sustainable construction products and alternative fuel vehicles. The event is a community partnership of the Coachella Valley Association of Governments with Southern California Edison, Southern California Gas Company, and the Building Industry Association. Call 760-346-1127 for more information.

Next Public Arts Concert April 29

The last of this year’s Public Arts Commission “Live Arts” concerts will be at the Cathedral City Library Community Room on Sunday, April 9th, at 3 PM. Cathedral City’s own chamber ensemble, Canyon Classics, will present a program entitled “April in Paris – music by favorite 19th and 20th century French composers.” The ensemble consists of a flute, violin, clarinet and piano (played by the humble writer of these news briefs). The concert will consist of music by Ravel, Debussy, Poulenc, Massenet and Saint-Saëns.

A special performance, just for children, of “The Story of Babar the Little Elephant” for narrator and piano with music by Poulenc will be given at 1:30 PM the same day in the community room. The half-hour work, based on the first book of the Babar children’s series by Jean de Brunhoff, will also be performed as part of the main concert at 3 PM for the general public. The concert is made possible in part by a grant from the Riverside Community Foundation.

Important Cathedral City Cove
Phase 1
Construction Information for week of April 2, 2007


Project Status Map

Accomplishments

bullet

500 laterals completed as of 3/30/07

bullet

5.9 miles of sewer mainline constructed as of 3/30/07

Work Scheduled Week of 4/2/07:

The list below represents the best available information for work scheduled during the upcoming week of 4/2/07. The contractor regularly provides door hanger notices prior to work being done to individual residents on streets where construction is planned.

Please Note:

Cove residents may see construction workers in areas throughout the Phase 1 Cove project that are not shown on the list below. This work could be related to surveying, material testing, inspection, contractor punch-list items, and field conditions resulting in unplanned work activity.

Sewer Work in process

Continuing work on Kings Road and southerly up Palo Verde Drive towards Terrace Road for sewer mainline, laterals, and manholes.

Continuing work on Grove Street between W. Buddy Rogers Drive and Cathedral Canyon Drive for sewer mainline, laterals, and manholes.

Beginning work on Tahquitz Road between Cathedral Canyon Drive and westerly towards Melrose Drive for sewer mainline, laterals, and manholes.

Asphalt Paving

Asphalt paving is complete on D Street, E Street, Encelia Lane, F Street, San Jacinto Road (west of Van Fleet), H Street, Iroquois Street, J Street, Van Fleet Avenue, and Glenn Avenue.

However, the Contractor will be raising sewer manholes, water valves, compacting parkways, and completing miscellaneous tasks on the above mentioned streets.

Note: San Jacinto Road (east of Van Fleet) and Chuperosa between H Street, Encelia Lane, and Terrace received base paving only. Additional paving will be part of next paving activity.

Street Work in process

bullet

D Street

bullet

Encelia Lane

bullet

San Jacinto Road (east of Van Fleet)

bullet

Chuperosa Lane

bullet

Las Tunas Way

bullet

Nightingale Road

bullet

Sharpless Road

bullet

Bel Air Drive

bullet

Dorn Drive

bullet

Desert View

bullet

Mountain View

bullet

Vista Drive

Water Line Work in process

bullet

Moonlight Drive

bullet

Treasure Trail

bullet

Indigo Lane

bullet

Kathy Drive

bullet

Vicki Lane

bullet

Chris Drive

Storm Drain Work in process

Continuing Storm drainage inlet installation on Terrace Road at Chuperosa Lane easterly to Palo Verde Drive.

Detours will be in place to divert traffic around drainage inlet construction. This work will be done in three phases and will have detours as follows:

Phase 1: Detour on Terrace Road between Cathedral Canyon Drive and Porter Drive

Phase 2: Detour on Terrace Road between Porter Drive and Dorn Drive

Phase 3: Detour on Terrace Road between Dorn Drive and Palo Verde Drive.

For more information on the Cove Improvement Project
please call the
COVE HELPLINE: (760)  250-8673
Click here for more information Cove Improvement District Home Page

 

Important Cathedral City Dream Homes
Construction Information for week of 4/2/2007:


Completed Sewer & Water Construction
as of 03-12-07

***ACCOMPLISHMENTS***
 
bulletCongratulations to 30220 & 30644 San Joaquin for being the 10th and 11th connection to the new sewer!
bulletSewer installation has begun in phase two
bulletBase paving has begun in phase one and should be finished by next week. Base paving is currently underway on San Luis Rey between Mission and Agua Caliente Elementary School.
bullet2 of approximately 4.5 miles of sewer mainline installed as of 4-2-07 (44% complete)
bullet246 of approximately 544 sewer laterals installed as of 4-2-07 (45% complete)
bullet40 of approximately 98 manholes installed as of 4-2-07 (41% complete)
bullet11 of approximately 33 fire hydrants installed as of 4-2-07 (33% complete)
bullet1.8 of approximately 4.5 miles of water mainline installed as of 4-2-07 (41% complete)
bullet216 of approximately 544 domestic water services (water laterals) installed as of 4-2-07 (40% complete)
bulletProject is ON SCHEDULE!

Completed Sewer & Water Construction as of 4-2-07

Sewer and water main as well as manholes, laterals and domestic services have been installed on the following streets:

bulletSan Joaquin Dr. between Mission Dr. and San Mateo
bulletIntersection of San Luis Rey and Ramon
bulletSan Luis Rey between Ramon and Agua Caliente School
bulletMission Dr. between San Luis Rey and San Diego up to San Gabriel Circle
bulletMission & Laguna Courts and San Clemente
bulletSanta Barbara Drive between San Luis Rey and San Diego
bulletSan Gabriel Circle between San Luis Rey and San Diego

Completed Sewer Construction as of 4-2-07

Sewer main and manholes have been installed on the following streets:

bulletSan Gabriel Circle between San Luis Rey and San Jose

Sewer laterals have been installed on the following streets:

bulletSan Gabriel Circle between San Luis Rey and San Jose

Upcoming Sewer & Water Construction for Week of 4-2-07:

Sewer work:

bulletSewer main, manholes and laterals will be installed on the following streets:
bulletSan Gabriel Circle between San Luis Rey and San Jose
bulletSanta Barbara between San Luis Rey and San Antonio

Water work:

bulletCrews will be installing remaining domestic water services in phase one. That will wrap-up water construction
bulletDisinfection has begun for all waterlines in phase one and will continue throughout the duration of the week
bulletDesert Water Agency will continue installing new water meters in phase one

Paving:

bulletBase paving on San Luis Rey between Mission and Agua Caliente Elementary School

Curb Restoration:

bulletCurb restoration will continue in phase one until all sewer clean-out lids and water meters have been installed

***IMPORTANT NOTES***

Connection to the sewer will not be allowed FOR ANY AREA until streets are base paved, manholes raised to base grade and lids are installed on sewer clean-outs. Notice will be given to property owners by the City and Water Agency when that time arrives.